Renovation of Hyvinkää Hospital
In Hyvinkää Hospital, we are building new facilities for the Dialysis Unit and the catheterization laboratory.
In 2024, we are building new facilities for the Dialysis Unit on the first floor of the building section D, and for the catheterization laboratory on the P floor of the building section C.
The catheterization laboratory will have full scale facilities near the hospital’s CCU and ICU, allowing us to make the most of synergies, for example in situations where the units need to assist each other. In addition to the procedure room, the facilities will include an appointment room and a monitoring room for four patients.
PROJECT INFORMATION
- Hyvinkää Hospital’s year of construction: 1975
- Location: Hyvinkää
- Owner: HUS
- Renovation developer: HUS Real Estate Ltd
Dialysis Unit
- Construction time: 2023–2024
- Lead designer: Raami Architects
- Size: 607 brm²
- Cost estimate: MEUR 2.15
Catheterization laboratory
- Construction time: 2024
- Lead designer: Lukkaroinen Arkkitehdit Oy
- Size: 245 brm²
- Cost estimate: MEUR 0.8
Previous renovations in Hyvinkää Hospital
We have renovated the inpatient ward floors 3 and 4 in section A of Hyvinkää Hospital into modern surgical wards. We’ve also remodeled the 5th floor and repaired the façade of the building’s section A.
After the renovation, the inpatient wards on the floors 3 and 4 have 80 patient beds in total. The renovation was completed in late 2023.